Southwest
The left lane on the dual lane exit ramp from eastbound Glenmore Trail to southbound 14 Street S.W. will be closed and the speed limit lowered to 50 km/h from 10 a.m. to 2 p.m. Tuesday, April 23 to allow for roadway maintenance.
 
Southeast
Motorists heading east on Stoney Trail/Highway 22X will shift to westbound lanes between Cranston Boulevard/McKenzie Lake Boulevard S.E. and Deerfoot Trail from Wednesday, April 24 to Friday, April 26 between 10 p.m. to 6 a.m. for the new Stoney Trail bridge construction.

Southbound Macleod Trail (1 Street S.E.) between 9 Avenue S.E. and 8 Avenue S.E. will have two left lanes closed from 9 a.m. to 3 p.m. daily, between Monday, April 22 to Thursday, April 25, for Enmax utilities.

Southbound Deerfoot Trail speed will be reduced to 50 km/h in the construction zone and motorists may experience delays from April 21 until May 10, for trucks moving materials from Deerfoot Trail S.E. between highway 22X and Cranston Avenue/Seton Boulevard S.E.

Northbound 3 Street S.E. at 7 Avenue S.E., the right lane will be closed. In addition, the eastside of sidewalk on 3 Street S.E. north of 7 Avenue S.E. will be closed. This will start at 9 a.m. on Monday, April 15 until 6 p.m. on Friday, May 10, for construction.

68 Street S.E. between 106 Avenue S.E. and 108 Avenue S.E. will have all traffic shifted to an adjacent eastside road, to allow for utility installations and surface upgrades, starting at 10 a.m. Wednesday, March 6. The speed limit of the detour road will be reduced to 30 km/h. This stage of construction is expected to last until mid-May. Updates will be provided as the project progresses.
 
100 Street S.E., between Glenmore Trail and Venture Avenue, will be closed for approximately six weeks starting at 10 a.m. Tuesday, April 2 to allow for water service upgrades and utility connections. Traffic will be directed to 84 Street S.E. to bypass the construction. Local business access will be maintained.
 
Northeast
Southbound 36 Street N.E. at the Rundle CTrain station the left lane will be closed, from 9 a.m. to 3 p.m. on Tuesday, April 23 for the NE CTrain platform extension project. For more information please visit www.calgary.ca/4carplatforms.
 
Southbound 36 Street N.E. at Marlborough CTrain station the left turn lane will be closed, from 9 a.m. to 3 p.m. daily, between Monday, April 22 until Friday, April 26, for the NE CTrain platform extension project. For more information please visit www.calgary.ca/4carplatforms.

36 Street N.E. will be closed between 80 Avenue N.E. and Country Hills Boulevard, beginning Monday, April 8, between Airport Trail and Country Hills Boulevard for the roadway to be reconstructed from two lanes to four lanes. The closure, which will last approximately four months, will allow Airport Trail connections to be made to 36 Street N.E. eastbound from the Airport Trail tunnel. Motorists are advised to use Métis Trail N.E. as an alternative route. For more information, visit 36 Street N.E. road reconstruction and widening.
 
Northbound Barlow Trail N.E. at 100 Avenue N.E., will be reduced to one lane. In addition, eastbound 100 Avenue N.E. at Barlow Trail will be closed. Motorists are advised to use Freeport Boulevard as an alternative route. Starting at 9 a.m. on Monday, April 15 and lasting until 6 p.m. Tuesday, April 23, for utilities upgrades.
 
Northwest
Eastbound 16 Avenue N.W.  at Crowchild Trail will be reduced to one lane, from 9 a.m. to 3 p.m. daily, between Monday, April 22 until Wednesday, April 24,  for sound wall repair.
 
Eastbound 16 Avenue N.W. between 10 Street N.W. and 2 Street N.W. will be reduced to one lane, from 8 p.m. on Tuesday, April 23 to 5 a.m. on Wednesday, April 24, for landscaping.

Evanspark Boulevard between Evanston Drive N.W. and Evansview Gate N.W. will be closed from Monday, April 22 at 9 a.m. until 6 p.m. on Friday April 26.

Lane closures on Centre Street between Laycock Drive and Thorncrest Road will restrict traffic to a single lane in each direction starting at 4 a.m. on Monday, April 22, for the Centre Street Reconstruction and Transit Priority project. Construction will last for approximately six to eight weeks.  Expect delays.  For more information, please visit www.calgary.ca/centrestreet.
 
Westbound 16 Avenue N.W. west of Sarcee Trail, one lane will be closed, 8 a.m. to 3 p.m. daily, from Tuesday, April 9 until Friday, May 3, for noise wall replacement.
 
This work is part of a number of ongoing road closures and lane restrictions in Calgary. For more information on these and other closures, please visit www.calgary.ca/trafficinfo.
-30-
Public Contact Information:
The City of Calgary, 311 Operations Centre.
Phone: 311 or from outside the local calling area phone 403.268.CITY (2489).
Public Web Contact: Complete and submit the Contact Us/Feedback form.