Calgary, AB,
01
August
2017
|
15:35
America/Denver

Calgary road closures - August 1, 2017

Calgary road closures – August 1, 2017

This press release is aimed at informing 911 and the media of major road closures and lane restrictions. For information on closures in your area, visit Calgary.ca/trafficinfo. Find up to the minute road closure information on the Transportation Twitter account (@yyctransport).

Northeast

Reduced lane northbound on Marlborough Way N.E. at Maryvale Drive N.E. beginning on Monday, July 31 to Thursday, Aug 3 daily from 8 a.m. to 3:30 p.m. Pedestrian detours indicated via signage. Closure is to accommodate utility work.

Reduced lane eastbound on Memorial Drive N.E. between 9 Street N.E. and 12 Street N.E. beginning on Tuesday, August 1 to Friday, August 4 daily from 7 a.m. to 3 p.m. Speeds will be reduced to 60 km/h through work area with a flagman onsite. Closure is to accommodate construction.

Reduced lanes eastbound and westbound on Country Hills Boulevard N.E. between Metis Trail N.E. and 52 Street N.E. from Monday, July 31 to Friday, August 4 daily from 9 a.m. to 3 p.m. Speeds reduced to 50 km/h through the work area. Closure is to accommodate construction.

Reduced lanes northbound and southbound on Skyview Ranch Drive N.E. between Skyview Ranch Crescent N.E. and Skyview Springs Common N.E. beginning on Monday, July 31 at 7 a.m. to Friday, August 4 at 7 a.m. Pedestrian detours indicated via signage. Closure is to accommodate utility work.

Reduced lane westbound on McKnight Boulevard N.E. west of 68 Street N.E. beginning on Monday, July 31 to Wednesday, August 2 daily from 10 a.m. to 1 p.m. Speed reduced to 50 km/h through work area. Closure is to accommodate construction.

Reduced lane eastbound on 16 Avenue N.E. between Barlow Trail N.E. and 36 Street N.E. beginning on Monday, July 31 to Wednesday, August 2 daily from 10 a.m. to 1 p.m. Speed reduced to 50 km/h through work area. Closure is to accommodate construction.

Reduced lanes northbound and southbound on 52 Street N.E. between Country Hills Boulevard N.E. and Skyview Parade N.E. beginning on Monday, July 31 at 8:30 to Saturday, August 5 at 6 p.m. Closure is to accommodate construction.

Various reduced lanes eastbound and westbound on 64 Avenue N.E. at 68 Street N.E. with reduced northbound/southbound lanes on 68 Street N.E. at this intersection. Work to begin on Wednesday, July 26 to Thursday, August 10 daily from 8:30 a.m. to 3:30 p.m. Closures are to accommodate utility work.

Reduced lanes westbound Memorial Drive N.E. between 68 Street and Madigan Drive N.E. starting Monday, July 24 at 8:30 a.m. until Friday, August 4 at 3:30 p.m. Closure is to accommodate sidewalk installation.

Reduced lanes eastbound 16 Avenue at Edmonton Trail N.E. weekdays starting Thursday, July 13 until Friday, August 25 from 8:30 a.m. to 3:30 p.m. This work accommodates construction.

Reduced lane northbound on 52 Street N.E. at Whitehorn Drive N.E. / Temple Drive N.E. beginning on Monday, July 10 to Friday, September 1 on weekdays only daily from 8:30 a.m. to 3:30 p.m. Pedestrian detour will be indicated via signage. Closure is to accommodate construction.

Reduced lanes northbound and southbound on Falconridge Boulevard N.E. at Taradale Drive N.E./Martindale Boulevard N.E. beginning on Tuesday, July 4 to Friday, September 1 (subject to change) on weekdays only from 8:30 a.m. to 3:30 p.m. Pedestrian detours will be indicated via signage. Closure is to accommodate construction.

Reduced lane northbound on 52 Street N.E. at Temple Drive N.E. / 44 Avenue N.E. beginning on Tuesday, July 4 to Wednesday, August 30 (subject to change) on weekdays only from 8:30 a.m. to 3:30 p.m. Closure is to accommodate construction.

Reduced northbound and southbound lanes on Falconridge Boulevard N.E. at Taradale Drive N.E. weekdays only from 8:30 a.m. to 3:30 P.M. beginning on Tuesday, June 27 to Thursday, September 7. Pedestrian detour indicated via signage. This closure is to accommodate transit construction work.

Northwest

NEW: Reduced southbound lane on 29 Street N.W. between Parkdale Lane N.W. and Parkdale Boulevard N.W. beginning on Wednesday, August 2 to Tuesday, August 8 (excluding Monday, August 7) daily from 9 a.m. to 3 p.m. Pedestrian and cycle track detours will be indicated via signage. Closure is to accommodate construction.

Reduced lanes eastbound and westbound on 16 Avenue N.W. between 46 Street N.W. and 49 Street N.W. beginning on Tuesday, August 1 to Thursday, August 3 daily from 9 a.m. to 3 p.m. The eastbound left turn from 16 Avenue N.W. onto Home Road N.W. will be restricted. Closure is to accommodate utility work.

The ramp from southbound Sarcee Trail N.W. to westbound 16 Avenue N.W. is closed beginning at 6 a.m. on Monday, July 24. During this closure, traffic will be detoured to 69 Street N.W. This closure continues until 5 a.m. on Monday, August 7 and accommodates road construction.

16 Avenue N.W. at 29 Street N.W. / Uxbridge Drive N.W. will see various lane closures until the end of October, 2017 as part of an intersection improvement project.

16 Ave NW / Bowfort Road Interchange Improvements

  • Daily lane reductions on Bowfort Road N.W. and 16 Avenue N.W. through the project limits from 9 a.m. to 3 p.m. until further notice. For more information on this project, visit the project page.

Stoney Trail/ Sarcee Trail Interchange Improvements

  • Daily lane reductions on Sarcee Trail N.W. and 16 Avenue N.W. through the project limits from 9 a.m. to 3 p.m. until further notice. For more information on this project, visit the project page.

Southeast

Reduced lane westbound on McKenzie Lake Boulevard S.E. from Mt. McKenzie Drive S.E. to Mountain Park Circle S.E. beginning on Monday, July 31 to Friday, August 4 daily from 9 a.m. to 3 p.m. Speeds will be reduced to 50 km/h through the construction zone. Pedestrian detour indicated via signage. This closure is to accommodate utility work.

Road closure on 4 Street S.E. between 58 Avenue S.E. and 60 Avenue S.E. beginning on Monday, July 17 at 8 a.m. to Friday, August 4 at 7 p.m. Access will be available to local traffic only. Vehicle detour indicated via signage. Closure is to accommodate utility work.

Road closure southbound on 3 Street S.E. between 6 Avenue S.E. and 7 Avenue S.E. with reduced northbound lanes beginning on Tuesday, June 20 at 12:00 a.m. until Friday, September 1 at 6 p.m. Vehicle and pedestrian detours indicated via signage. This closure accommodates construction.

17 Ave S.E. BRT Project

Macleod Trail / 162 Avenue Interchange Project

Southwest

UPDATE: Reduced lanes on 5 Street S.W. between 7 Avenue S.W. and 8 Avenue S.W. beginning on Friday, July 28 to Thursday, August 3 weeknights only from 7 p.m. to 4 a.m. Pedestrian access will be restricted along work area. Closure is to accommodate overhead plus fifteen work.

NEW: Road closure on 2 Avenue S.W. between 3 Street S.W. and 4 Street S.W. on Wednesday, August 2 from 9 a.m. to 6 p.m. Closure is to accommodate mobile crane. Pedestrian detour will be indicated via signage. Use alternate route.

NEW: Road closures on both 12 Street S.W. and 13 Street S.W. at 11 Avenue S.W. with reduced lanes on 11 Avenue S.W. between 11 Street S.W. and 14 Street S.W. There will be access to local traffic only on 12 Street S.W. and 13 Street S.W. with restricted parking on 11 Avenue S.W. Closure will begin on Wednesday, August 2 at 9 p.m. to Thursday, Aug 3 at 5 a.m. to accommodate utility work.

NEW: Reduced lanes northbound on 11 Street S.W. between 7 Avenue S.W. and 8 Avenue S.W. beginning on Wednesday, August 2 at 9 a.m. to Monday, August 14 at 4 p.m. This closure accommodates utility work.

NEW: Reduced lane southbound on 8 Street S.W. between 15 Avenue S.W. and 17 Avenue S.W. beginning on Wednesday, August 2 to Friday, August 4 daily from 9 a.m. to 3 p.m. This closure accommodates construction work.

Reduced lane eastbound on 9 Avenue S.W. between 8 Street S.W. and 9 Street S.W. beginning on Monday, July 31 at 9 a.m. to Tuesday, August 1 at 7 p.m. Pedestrian detour will be indicated via signage. Closure is to accommodate utility work.

17 Avenue S. reconstruction project

  • Road closure on 17 Avenue S.E. between 1 Street S.E. and Macleod Trail S.E. beginning on Monday, July 17 at 7 a.m. to Tuesday, August 8 at 7 p.m. Access will be open to local traffic only. Vehicle detours will be indicated via signage.
  • Road closure on 17 Avenue S.E. between Centre Street S.E. and 1 Street S.E. beginning on Monday, July 17 at 7 a.m. to Monday, August 14 at 7 p.m. Access will be open to local traffic only. Vehicle detours will be indicated via signage.
  • Road closure on 17 Avenue S.E. between 1 Street S.W. and Centre Street S.E. beginning on Monday, July 17 at 7 a.m. to Sunday, October 1 at 7 p.m. Access will be open to local traffic only. Vehicle detours will be indicated via signage.
  • 17 Avenue will be closed to traffic between Macleod Trail and Centre Street starting May 19.
  • For more information on the 17 Avenue project visit Calgary.ca/17Avenue.
  • For more information, visit the construction schedule page.

Alberta Transportation

Alberta Transportation maintains Deerfoot Trail (Hwy.2) and Stoney Trail (Hwy. 201). For more information on work happening on these roads visit Alberta Transportation’s website.

Southwest Ring Road Project

24 Street S.W. is permanently closed north of Highway 22x as part of the SWRR construction project. For more information on work happening, visit http://www.swcrrproject.com/traffic-updates/