Water use stays in green zone as feeder main connection work reaches final stages

Calgary and neighbouring communities continue to keep their water use in the green zone—below the daily target of 500 million litres—as we work through the final stages of the Bearspaw Feeder Main connection work. 

Yesterday, water demand was 491 million litres. 

Construction update 

Work is progressing and remains on track at all worksites.  

  • At the Shaganappi Pump Station, the pipe has been connected and inspected and is ready to receive water. 
  • At 89 Street and 33 Avenue, pipe connection work and valve connections are ongoing.  
  • At 83 Street and 33 Avenue, pipe connection is ongoing and expected to be completed later today.  
  • Pipe installation is complete at all five locations along Parkdale Boulevard and Memorial Drive N.W. Backfilling and surface rehab are underway. Parkdale Boulevard is expected to return to regular traffic flows by the end of next week. 