New Bearspaw Feeder Main reaches construction milestone as preparations for return to service begin

After 11 months of work, the Bearspaw Feeder Main Replacement project has reached a major milestone: the new feeder main is now fully built and connected to our water system.

Before the new pipe can be put into service, it must be pressure tested, cleaned, flushed and refilled, then pass water quality testing. This process will take a few weeks, and we expect the new pipe to be operational later in December.

While the new pipe is being commissioned, we need to temporarily bring the old pipe back into service. We expect to begin refilling the old pipe tomorrow. This will take about five days and require approximately 22 million litres of water. Once the pipe is full, we will test the water quality and check the system before opening valves and starting pumps at the Bearspaw Water Treatment Plant. If all goes as planned, we expect to lift water restrictions later next week.

Water Demand

Since water restrictions began on Nov. 4, Calgary and neighbouring communities have kept their daily water use in the green zone and below the target of 500 million litres every day.

Yesterday, water demand was 493 million litres.

Over the coming days, we expect the water demand numbers to rise to reflect the water used to refill the old pipe as well as some other work requiring water. The water used for refilling the old pipe will come from the Bearspaw Water Treatment Plant and won’t impact the amount of water that is available in the rest of our system or put additional stress on the Glenmore Water Treatment Plant.

Construction update

Work is progressing and remains on track at all worksites.

· At the Shaganappi Pump Station, the pipe has been connected and inspected and is ready to receive water.

· At 89 Street and 33 Avenue, pipe and valve connections are complete. Backfilling and paving are underway, and we will begin refilling this segment of pipe on Friday.

· At 83 Street and 33 Avenue, the pipe has been connected and inspected, and we will begin refilling this segment of pipe on Friday.

· Along Parkdale Boulevard and Memorial Drive N.W., backfilling and paving are complete, and we have also completed refilling this segment of pipe. Pressure testing will begin tomorrow. The pipe will then need to be drained and filled again, so those in the area may see water being released. This is necessary and part of getting the pipe ready for service. Parkdale Boulevard is expected to return to regular traffic flows by the end of next week.

Stay informed