Calgary, AB,
14
April
2016
|
15:35
America/Denver

Calgary road closures - April 14, 2016

Calgary road closures and lane restrictions – April 13, 2016

Find up to the minute road closure information on the Transportation Twitter account (@yyctransport)

Deerfoot Trail Street Sweeping

  • NEW: Northbound Deerfoot will be closed from Southland Drive to Peigan/Barlow from 9 p.m. on Monday, April 18 to 5 a.m. on Tuesday, April 19. Traffic will be detoured during this closure.
  • NEW: Northbound Deerfoot is closed between Southland Drive and 17 Avenue from 9 p.m. on Tuesday, April 19 to 5 a.m. on Wednesday, April 20.
  • Various single lane closures on Deerfoot Trail throughout the city nightly from Monday, April 3 through Thursday, April 21.

Northeast

NEW: The right lane of eastbound McKnight Boulevard at 36 Street N.E. is closed from 9 a.m. to 3 p.m. on Friday, April 15. This closure accommodates construction. Traffic turning off of southbound 36 Street N.E. will need to yield to eastbound McKnight traffic.

NEW: Single right lane closures on northbound and southbound 12 Street N.E. south of McKnight Boulevard N.E. from 9 a.m. to 3 p.m. on Friday, April 15 and Monday, April 18. This closure accommodates construction.

NEW: Various single lane closures on 64 Avenue N.E. between Metris Trail N.E. and 68 Street N.E. from 9 a.m. to 3 p.m. daily beginning on Friday, April 15. This construction continues daily during these hours until 3 p.m. on Tuesday, April 19 and accommodates LED streetlight installation.

NEW: Various single lane closures on 36 Street N.E. between Memorial Drive and 16 Avenue N.E. daily from 9 a.m. to 3 p.m. beginning on Friday, April 15. These closures accommodate curb rehab in preparation for paving, and continue until further notice.

NEW: 36 Street N.E. is reduced to a single left lane at 24 Avenue N.E. from 5:30 a.m. to 9 a.m. on Sunday, April 17. This closure accommodates utility work.

NEW: 4 Avenue N.E. is closed between Edmonton Trail N.E. and 4A Street N.E. from 7 a.m. to 5 p.m. on Friday, April 15. This closure accommodates construction.

NEW: 12 Street N.E. is closed between McKnight Boulevard N.E. and 45 Avenue N.E. beginning at 8 p.m. on Friday, April 15. There will be no access to McKnight Boulevard N.E. via 12 Street N.E. and motorists will be detoured via 19 Street N.E. This closure continues 10 p.m. on Sunday, April 17 and accommodates construction related to the McKnight Boulevard N.E. Widening Project.

NEW: 11 Street N.E. is closed south of 68 Avenue N.E. will be closed beginning at 7 a.m. on Saturday, April 16th to 7 a.m. on Monday April 18th. Beginning on Monday April 18, the closure will be on the north side of 68 Avenue N.E. to allow northbound traffic from 11 Street N.E. onto westbound 68 Avenue N.E. This closure continues until 7 a.m. on Monday, April 25.

NEW: 10 Street N.E. is closed between 1 Avenue and 2 Avenue N.E. beginning at 7 a.m. on Monday, April 18. This closure continues until 7 p.m. on Thursday, April 21 and accommodates utility work.

NEW: 13 Avenue N.E. is closed between Edmonton Trail N.E. and 2 Street N.E. from 7 a.m. to 7 p.m. on Monday, April 18. This closure accommodates construction.

NEW: The right lane and adjacent sidewalk of southbound 36 Street N.E. is closed at 25 Avenue N.E. from 9 a.m. to 3p p.m. on Monday, April 18. This closure accommodates construction.

Single right lane closure of northbound 12 Street N.E. south of McKnight Boulevard N.E. begins daily from 9 a.m. to 3 p.m. on Monday, March 28 until 3 p.m. on Friday, April 15. This closure continues daily during these hours on weekdays, and from 7 a.m. to 7 p.m. on Saturdays.

New traffic patterns on McKnight Boulevard N.E. between 12 Street N.E. and 19 Street N.E. until June 2016. Eastbound McKnight will be closed in this stretch and narrowed two-way traffic will be in place in the westbound lanes. This work is part of the McKnight Boulevard N.E. Widening Project.

The right lane of eastbound 16 Avenue N.E. at 1 Street N.E. is closed between 9 a.m. and 3 p.m. weekly on Tuesday through Friday until further notice. This closure accommodates construction.

Northwest

14 Street N.W. is reduced to one lane southbound between 2 Avenue N.W. and the Memorial Drive Bridge from 9 a.m. – 3 p.m. daily from Wednesday, April 13 until Tuesday, April 19 due to utility inspection.

The right lane of northbound 10 Street N.W. between Memorial Drive and 2 Avenue N.W. is closed from 9 a.m. to 3 p.m. daily beginning on Friday, April 8. This closure accommodates the Kensington improvements project and is expected to last daily through October 2016.

The right lane of northbound 10 Street N.W. between Memorial Drive and 2 Avenue N.W. is closed from 6:30 p.m. to 5 a.m. daily beginning on Monday, April 11. This closure accommodates the Kensington improvements project and is expected to last daily through October 2016.

Tuscany Way N.W. is closed between Tuscany Valley Green N.W. and 12 Mile Coulee Road N.W. beginning at 9 a.m. on Tuesday, April 5. During this closure traffic will be detoured via Tussellwood Drive N.W. This closure continues until 7 p.m. on Tuesday, April 19 and accommodates construction.

The right lane of eastbound 16 Avenue N.W. is closed at Bowfort Road from 9 a.m. to 7 p.m. starting Friday, April 1 and continuing daily during these hours until Friday, April 15 due to construction.

83 Street N.W. is closed between 33 Avenue N.W. and Bowfort Road N.W. until Spring 2016. There will be no access to Bowness Road N.W. from 16 Avenue N.W. during this closure; use an alternate route.

Southeast

NEW: Various single lane closures on Glenmore Trail north of 52 Street S.E. daily from 9 a.m. to 3 p.m. beginning on Friday, April 15. This construction continues daily during these hours on weekdays, and from 7 a.m. to 6 p.m. on weekends. These closures accommodate construction and continue until further notice.

NEW: Various lane closures on southbound and eastbound 146 Avenue S.E. at Bow Bottom Trail S.E. beginning at 8 a.m. on Thursday, April 14. During this closure, a two-way traffic will be in place in the westbound and northbound lanes. This closure remains in place until 8 a.m. on Tuesday, April 19 and accommodates construction.

NEW: 10 Avenue S.E. is closed between 3 Street S.E. and Macleod Trail S.E. from 8:30 a.m. on Thursday, April 14. This closure continues until 6 p.m. on Sunday, April 17 and accommodates water utility work.

NEW: The right lane of eastbound Glenmore Trail S.E. is closed west of 52 Street S.E. and the speed limit is reduced to 60 km/hr. from 9 a.m. to 3 p.m. on Friday, April 15. This closure accommodates construction.

NEW: 15 Street S.E. is closed between 42 Street and 46 Street S.E. beginning at 9 a.m. on Monday, April 18. During this closure, business access will be maintained. This closure continues through 2016 and accommodates major water services work.

Starting on Tuesday, March 29 and continuing until the end of April, there will be various stages of construction with sections of roadway being closed on 34 Avenue S.E. between Manchester Road and Dartmouth Road to allow for gas main upgrades. Use 36 Avenue S.E. to bypass the closures.

Zoo Road will be closed beginning on Monday, March 7 to accommodate the construction of the Zoo Flood mitigation project. The 12 Street S.E. bridge will remain open to local only traffic. This closure is expected to last until December 2017.

Blackfoot Trail / 58 Avenue S.E. Intersection Improvements Project

  • From now until late summer of 2016, there will be periodic lane closures and 50 km/h speed reductions at the intersection of Blackfoot Trail at 58 Avenue S.E. to allow for intersection improvements. Further information will follow as construction progresses. For additional information on this project, please go to Calgary.ca and search “58 Avenue and Blackfoot Trail S.E. intersection improvements”.

Macleod Trail / 162 Avenue Interchange project

  • The two left lanes will be closed on northbound Macleod Trail south of 162 Avenue S.E. / Sun Valley Boulevard from 10 p.m. Thursday, April 14 to 5 a.m. Friday April 15.
  • Starting on Thursday, April 7, the access to westbound 162 Avenue S.E. from northbound Macleod Trail will change. The previous northbound Macleod Trail to westbound 162 Avenue S.E. exit will re-open, but operate as a single left turn only. The access to eastbound Sun Valley Boulevard from northbound Macleod Trail will remain as is on the existing detour ramp.
  • Sunpark Gate between Sun Valley Boulevard and Sunpark Plaza will close starting Sunday, April 3. Traffic will be directed to use Sunpark Drive to bypass the closure. A 4-way stop at the intersection of Sunpark Drive with Sunpark Plaza will be installed on Friday, April 1 in an effort to minimize the impact to the surrounding road network as a result of the closure.
  • The dual turns from eastbound and westbound 162 Avenue S.E. to northbound and southbound Shawville Boulevard will be revised to single left turns starting Sunday April 3. An alternate access to the south end of Shawville Boulevard can be used via the southbound Macleod Trail exit ramp to 22X.

Glenmore Trail / Ogden Interchange

  • NEW: Southbound Shepard Road between Glenmore Trail and 84 Avenue S.E. will be closed from 9 p.m. Friday, April 15 until 5 a.m. Monday, April 18 for utility upgrades related to the Glenmore Trail / Ogden Road interchange project. Local traffic will be detoured to Barlow Trail to bypass the construction. Alternate routes are recommended as delays are expected.
  • Construction continues at the Glenmore / Ogden Interchange. For information on this project, visit the Glenmore / Ogden Interchange website on Calgary.ca

Southwest

NEW: 2 Street S.W. is reduced to a single lane in each direction between 11 Avenue and 12 Avenue S.W. beginning at 8 a.m. on Friday, April 15. This closure continues through 6 p.m. on Monday, April 25 and accommodates construction.

NEW: The left lane and adjacent sidewalk of 6 Avenue S.W. are closed west of Centre Street S from 9 a.m. to 3:30 p.m. on Friday, April 15. This closure accommodates sign installation.

NEW: 2 Street S.W. is reduced to a single right lane at 8 Avenue S.W. from 6 p.m. on Thursday, April 14 to 6 a.m. on Friday, April 15. This closure accommodates glass work.

NEW: The left lane and adjacent sidewalk of 6 Avenue S.W. are closed east of 3 Street S.W. beginning at 6 p.m. on Friday, April 8. This closure continues until 3:30 p.m. on Friday, April 15 and accommodates construction.

NEW: 5 Street S.W. is closed between 6 Avenue S.W. and 8 Avenue S.W. beginning at 7 p.m. on Friday, April 15. Cycle track will be detoured to 4 Street and 7 Street S.W. This closure continues until 10 p.m. on Sunday, April 17 and accommodates construction.

NEW: 2 Street S.W. is reduced to a single right lane at 8 Avenue S.W. from 6 a.m. to 10 p.m. on Sunday, April 17. This closure accommodates glass work.

NEW: Westbound 10 Avenue S.W. is closed at 5 Street S.W. daily from 9 a.m. to 3 p.m. beginning on Monday, April 18. During this closure there will be various lane closures on 10 Avenue between 5 Street and 6 Street S.W. Eastbound traffic will be maintained. This closure continues daily during these hours until Friday, April 22 and accommodates utility work.

NEW: 16 Avenue S.W. is closed from 12 Street S.W. to 14 Street S.W. beginning at 8 a.m. on Monday, April 18. During this closure, 12 Avenue S.W. is also closed at from 15 Avenue S.W. to 16 Avenue S.W. This closure remains in place until 5 p.m. on Wednesday, April 20 and accommodates crane work.

NEW: Left lane closure on 37 Street S.W. north of 41 Avenue S.W. beginning at 9 a.m. on Monday, April 18. This closure continues until 3 p.m. on Friday, April 29 and accommodates utility work.

The left lane and adjacent sidewalk of 6 Avenue S.W. is closed west of 2 Street S.W. beginning at 6 p.m. on Friday, April 8. This closure continues until 3:30 p.m. on Friday, April 15 and accommodates construction.

The cycle track and adjacent parking lane will be closed at 8 Avenue S.W. between 10 Street and 11 Street S.W. beginning at 8 a.m. on Monday, April 11. Cycle track and vehicle traffic are asked to share the road westbound on 8 Avenue S.W. This closure continues until 9 p.m. on Wednesday, April 13 and accommodates construction.

Crowchild/Flanders Ave Interchange

  • NEW: The southbound Richard Road off ramp and temporary access ramp into Currie Barracks will be closed on Friday, April 15 between 5 a.m. and 10 a.m. for concrete work.
  • The northbound exit ramps from Crowchild Trail S.W. to Flanders Avenue S.W. are currently closed until late 2016. Motorists will be unable to access Flanders Avenue S.W. via northbound Crowchild Trail S.W. Motorists are advised to use 33 Avenue S.W. or 50 Avenue S.W. via Crowchild Trail as alternate routes.
  • Caen Avenue (from the Currie Business Park entrance to Quesnay Wood Drive) is closed to allow for the utility work necessary for the Interchange construction. This stretch of Caen Avenue will be closed until late 2016. A temporary off-ramp provides access into the Currie Business Park, from Crowchild Trail South to Battleford Avenue.
  • Construction work has begun on Richard Road and eastbound Flanders Avenue. Traffic on Richard Road will be reduced to one lane in each direction (north and sound bound).

Alberta Transportation

For more information visit Alberta Transportation’s website.

Follow The City of Calgary’s Transportation Department on Twitter for up to date information on road closures, projects and all of Transportations’ services at @yyctransport.

Visit Calgary.ca/trafficinfo for up-to-date road closure and incident information.